Phase 1A – 30th June 2022

Phase 1A includes the following requirements:


  • Smart Functionality
  • Electricity Supplier Interoperability
  • Loss of Communications Network Access
  • Safety
  • Measuring System
  • Off-peak charging
  • Randomised Delay
  • Assurance
  • Register of Sales


Phase 1B – 30th December 2022

Phase 1B includes the following requirements:


  • Security


Phase 2 –  Under Development (Expected in 2024)


The second Phase of smart charging regulations is currently being scoped, with an industry consultation later in 2022. They are expected to include other types of energy smart appliances like home batteries and heat pumps, defining minimum standards for the Demand Side Response systems that control these loads.  

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article